Concrete volume calculator

Concrete is ordered by volume with a waste allowance, and short-ordering a pour is far more expensive than over-ordering. Enter the element dimensions and quantity to get the volume in every unit a supplier might quote, plus the bag count for small hand-mixed pours.

concrete volume calculator

Volume to order
3.78
Net volume
3.6 m³ (127.13 ft³)
Cubic yards
4.94yd³
25 kg bags (hand mix)
382 bags ≈ 9.07 t

Formula

volume = length × width × thickness × quantity × (1 + waste %)

Assumes 2400 kg/m³ for normal-weight concrete and roughly 0.95 m³ of set concrete per m³ of dry mix. Deduct large openings and column heads separately rather than averaging thickness.

Worked examples

InputResult
6 × 4 m slab at 150 mm3.6 m³ net, 3.78 m³ ordered at 5% waste
10 pad footings 1 × 1 × 0.6 m6.0 m³ net, 6.3 m³ ordered
300 × 300 mm column, 3 m tall0.27 m³ each

Questions

How much waste should I allow on a concrete order?

5% for a clean slab on a level formation, up to 10% for footings on uneven ground or pours with heavy reinforcement congestion. Confirm the supplier's minimum load and part-load charge before trimming the figure.

How many 25 kg bags make a cubic metre?

Roughly 100–110 bags of dry mix per cubic metre of placed concrete. Anything above about 0.5 m³ is cheaper and far more consistent as a ready-mix delivery.

Can I take this quantity from a Revit model?

Yes — schedule the structural element volume parameter rather than deriving it from dimensions, then add the waste allowance outside the model. Model volume is net and excludes formwork tolerance and spillage.